Ampd Powered Theme Park Running Event

Background
Introduction & Project Information
Client: A major, global multinational mass media, entertainment and theme park conglomerate
Project location: Lantau Island, Hong Kong
Project type: Weekend running event
Delivery date: November 2025
Project brief: While a grid connection was available at the event location, the available capacity was insufficient for the loads. At the same time, due to issues of brand image and the healthy living message which the event organisers and sponsors were aiming to promote, diesel generators were ruled out as an option to meet the additional powers needs of the event.
The client contacted Ampd Energy to propose a solution which met the needs of the event.
CO2 reduction
quieter than a diesel generator
reliability. Provided stable power supply for the event.
air quality pollutants leading to a better event environment
The Challenge
The Solution
Results
Four Ampd Enertainer units were successfully deployed at various locations to support the 10K, 5K, and 3K run events over the weekend. The existing available grid capacity was utilized for continuous charging, with state-of-charge (SoC) monitored for the entire duration of the event. Both the event organizer and their electrical and mechanical (E&M) contractor expressed their satisfaction with the power and energy proposal, on-site technical support, and Enernet IoT monitoring system.
Download Case Study
Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.

Download Case Study
Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.








.png)